Village Greens Circle and Edgewater Lane

Village Greens Circle & Edgewater Lane
Project ID: 
1500/2500/4500/7500
Project Type:
Capital Project
Project Status: 
Design
Design Engineer: 
Wallis Engineering
Contractor: 
TBD
Location: 
Charbonneau Wilsonville, OR 97070

PROJECT DESCRIPTION

Repair or replace roadways and utilities.  

STAFF CONTACTS

Staff can be reached via telephone at 971-325-4080.

Marissa Rauthause, Civil Engineer 

 

 

Project Location Map
Status Updates
  • Preliminary design and survey began in July 2022. 
  • Design completed in October 2023.
  • Franchise utility relocation to begin in early 2024 and continue through mid-2024.  The franchise utilities to be relocated may include Portland General Electric power and street lighting, Century Link communication and fiber, Comcast cable and Northwest Natural Gas.  Project utility and street repair construction to begin after franchise utility relocation is complete.